mgt311 Assignment

0 comments

A:


Question(s):

Question 1:

Workers should be given more control over the inspection for their own work. Discuss the pros and cons of this situation?

Question 2:

  • What are the advantages of Exponential smoothing over the Moving average and the Weighted moving average?
  • Explain the aggregate planning strategy?

Question 3:

Sequence the jobs shown below by using a Gantt chart. Sequence the jobs in priority order 1, 2, 3, 4.

Job Work Center/Machine Hours Due Date (days)

1

A/3, B/2, C/2

3

2

C/2, A/4

2

3

B/6, A/1, C/3

4

4

C/4, A/1, B/2

3

  • Using finite capacity scheduling, draw a Gantt chart for the schedule
  • What is the makespan?
  • How much machine idle time is there?
  • How much idle time (waiting time) is there for each job?
  • When is each job delivered?
  • Which department is the bottleneck?
  • Calculate the machine utilization?

most have reference

  • Avoid plagiarism, the work should be in your own words, copying from other resources without proper referencing not allowed . No exceptions.

About the Author

Follow me


{"email":"Email address invalid","url":"Website address invalid","required":"Required field missing"}