This is graded homework. Include a problem statement with each problem.

Put your name, course,

assignment number, and page number at the top of each page.

1

. (5 points)

Create an MS Project schedule for the project above. Assign the activities fixed

costs as shown in the table. Submit a network diagram for the entire project that fits on a

single landscape page. Format the nodes only to have task name and duration. Arrange

activity nodes and format the page for clarity (

no tiny printing

).

2

. (5 points)

Create an Early Start cash flow bar chart and S-Curve for the project without

imposing any constraints. Submit a plot of the S-Curve superimposed on the cash flow bar

chart by month.

3

. (6 points)

Set the baseline for your original early start schedule. Adjust the schedule to keep

cash flow (progress payments) under $110,000 per month. Use any technique that you like.

Submit a Tracking Gantt Chart view showing the original baseline and your revised schedule.

Also submit and a cash flow bar chart and S-Curve plot for the revised schedule.

4

. (5 points)

Start with your original schedule and add the resource “D8” to the activities to

track the number of bulldozers needed. Print out a “Resource Graph” view showing utilization

of D8 bulldozers.

5.

(6 points)

Repeat problem 4 but constrain the schedule so that you do not exceed 10 D8

bulldozers in any month. Use any method that you like but explain what you did.